It will take up to 15 business days to complete a standard work request (unless a specific date has been agreed directly with you). Please note the following exceptions:

  • A safe environment (nothing to prevent installation such as a loose switchboard, exposed wires or a point of attachment that is too high or low).
  • Clear access to the meter box
  • Unlocked gates
  • Installing the meter will not disrupt another customers electricity supply
  • For complex meter exchanges the distributor needs to undertake any supply related pre-work prior to the meter being installed
  • If you have life support equipment, an appointment is always required
  • You don't have an agreement with us to install the meter.