Hi there,
How many wells have been decommissioned in the Camden Gas Project area in 2019-2020? Please give me a list of the wells decommissioned.
Thanks
Dan
Thanks for your question Dan.
We are happy to report that we are on track to progressively decommission wells and rehabilitate sites at Camden prior to ceasing production in 2023.
In FY 19 (July 2018 – June 2018), 9 wells were decommissioned.
In FY 20 (July 2019 – June 2020), 14 wells were decommissioned.
More information about the decommissioned wells is outlined in the AGL Camden Gas Project 2019-2020 Annual Environmental Performance Report available on our website www.agl.com.au/camden
Cheers,
Lachlan
Thanks Lachlan,
Out of the 144 wells drilled in the Camden Gas Project how many have now been decommissioned?